Pittsfield is planning on doing repair work on a number of roads this summer.
A complete list of the streets and work follows below.
Work will be starting with pulverizing Meadow, Shady, Briar and River Lane the week of June 7th, 2021. These roads will be left as gravel to compact until the completion of the work in early July. The road will be regraded prior to finishing.
Patching and spot repairs will also occur during June. The sealing and finishing will occur in early July, dependent on weather delays.
The Town will NOT hold a meeting to answer questions about the work.
If you have questions, please contact Chairman Deneys at (920) 865-1200 or the Town Engineer Paul Willis at (920) 593-6854
List of roads and work:
- Meadow Dr. — 1795 ft. X 18 ft. — Pulverize add 4″ of road gravel then apply a DOUBLE hot oil chip seal coat -(Final Grade, water, roll and Vacuum)
- Shady Lane Dr. — 1320 ft. X 18 ft. — Pulverize add 4″ of road gravel then apply a DOUBLE hot oil chip seal coat -(Final Grade, water, roll and Vacuum)
- Briar Dr. –1850 ft. X 16 ft. — Pulverize add 4″ of road gravel then apply a DOUBLE hot oil chip seal coat -(Final Grade, water, roll, and Vacuum)
- River Lane Dr. — 530 ft. X 16 ft. — Pulverize add 4″ of road gravel then apply a DOUBLE hot oil chip seal coat -{Final Grade, water, roll, and Vacuum)
- Pine Ridge Ct. –1270 ft. X 20 ft. –Apply a Single hot oil chip seal coat and 110 ton cold mix wedging in various bad spots
- Sumac Dr. –1270 ft. X 22 ft. — Apply a Single hot oil chip seal coat and 77 ton cold mix wedging in various bad spots
- Sandhill Dr. — 2165 ft. X 22 ft. –Apply a Single hot oil chip seal coat and 143 ton cold mix wedging in various bad spots
- Angle Dr. — 900 ft. X 20 ft. –Apply a Single hot oil chip seal coat and 22 ton cold mix wedging in bad spots. NOTE The entire length of Angle Dr. is being completed in cooperation with the Town of Maple Grove. Only 900 feet is Pittsfield financial responsibility.