For several years the address at 5622 County Road B in the Town ship has been rented by a the property owner to the Department of Corrections (DOC) for the housing of sex offenders.
The Brown County Sheriff’s Office (even though they are not required to) has notified the Town that a new offender will be housed at this residence. Public notification is required for offenders based on their status in the State system. This offender actually does not require any public notification.
Wednesday June 16th, 2021, was Treasurer Sandy Harrig’s last day with the Town. She was honored at the Town Board Meeting on June 8th with a small gift and the below resolution.
The Town thanks her for her many years of dedicated service and wishes her the best in her retirement.
Pittsfield is planning on doing repair work on a number of roads this summer.
A complete list of the streets and work follows below.
Work will be starting with pulverizing Meadow, Shady, Briar and River Lane the week of June 7th, 2021. These roads will be left as gravel to compact until the completion of the work in early July. The road will be regraded prior to finishing.
Patching and spot repairs will also occur during June. The sealing and finishing will occur in early July, dependent on weather delays.
The Town will NOT hold a meeting to answer questions about the work.
If you have questions, please contact Chairman Deneys at (920) 865-1200 or the Town Engineer Paul Willis at (920) 593-6854
List of roads and work:
Meadow Dr. — 1795 ft. X 18 ft. — Pulverize add 4″ of road gravel then apply a DOUBLE hot oil chip seal coat -(Final Grade, water, roll and Vacuum)
Shady Lane Dr. — 1320 ft. X 18 ft. — Pulverize add 4″ of road gravel then apply a DOUBLE hot oil chip seal coat -(Final Grade, water, roll and Vacuum)
Briar Dr. –1850 ft. X 16 ft. — Pulverize add 4″ of road gravel then apply a DOUBLE hot oil chip seal coat -(Final Grade, water, roll, and Vacuum)
River Lane Dr. — 530 ft. X 16 ft. — Pulverize add 4″ of road gravel then apply a DOUBLE hot oil chip seal coat -{Final Grade, water, roll, and Vacuum)
Pine Ridge Ct. –1270 ft. X 20 ft. –Apply a Single hot oil chip seal coat and 110 ton cold mix wedging in various bad spots
Sumac Dr. –1270 ft. X 22 ft. — Apply a Single hot oil chip seal coat and 77 ton cold mix wedging in various bad spots
Sandhill Dr. — 2165 ft. X 22 ft. –Apply a Single hot oil chip seal coat and 143 ton cold mix wedging in various bad spots
Angle Dr. — 900 ft. X 20 ft. –Apply a Single hot oil chip seal coat and 22 ton cold mix wedging in bad spots. NOTE The entire length of Angle Dr. is being completed in cooperation with the Town of Maple Grove. Only 900 feet is Pittsfield financial responsibility.
Reconstruction work on Woodside Drive between County Road B and Forest Drive will occur starting the week of June 7th, 2021. Please plan you travel around the work.
The work will generally consist of grinding and milling portions of the current surface, adding material and then re paving.
The Town will NOT hold a public information meeting to answer questions about the work. Letters were sent to all property owners.
If you have questions, please contact Chairman Deneys at (920) 865-1200 or the Town Engineer Paul Willis at (920) 593-6854.
Due to the Memorial Day holiday, Town of Pittsfield garbage and recycling pickup scheduled for Monday May 31st will actually happen on Friday May 28th.
Please have your containers out by the roadside by 6 am on Friday.
Please join the Wisconsin Department of Transportation for a virtual construction update meeting (Monday, May 24, 2021 at 6:00pm) (link below) to discuss upcoming work taking place at WIS 32 from WIS 29 to the Village of Pulaski. Construction is currently scheduled to start Monday June 7, 2021 with the detour starting on Wednesday June 9, 2021. The intent of this meeting is to share details of work zone operations, staging, and traffic impacts. The construction contractor, Northeast Asphalt, will be available to answer questions and discuss any concerns. No in-person public meeting will be held due to the current health emergency.
This meeting will be held via Microsoft Teams so project staff and the contractor can share project visuals. It is recommended you install Microsoft Teams software prior to the meeting. It is free and relatively user friendly: https://www.microsoft.com/en-us/microsoft-365/microsoft-teams/download-app
The meeting details are as follows:
Virtual Public Construction Update · Monday, May 24, 2021 at 6:00pm · Access the virtual meeting by going to the WIS 32 project website and clicking the “go to meeting” link. · You can also call into the meeting and hear the audio via phone. Conference Call Phone #: 608-571-2209, Phone Conference ID: 818 545 666#
We have developed a project construction website with detailed construction information, traffic impacts and displays. The same information to be presented at the virtual construction update is available on the WIS 32 Project Construction website at https://projects.511wi.gov/wis32pulaski/.