Village of Howard Glendale Avenue Sanitary Sewer Construction update.

Because of ongoing issues with the depth of the sewer and dewatering in the past month, Contractor will continue to work on dewatering system early portion of the week. With plans to install sanitary main mid to later part of the week.

Glendale Avenue updated Schedule

  • Nature Ridge to Sunny Brook Drive: This segment is anticipated to be completed in November 2026.
  • Sunny Brook Drive to Alfred Way: Work on this portion is expected to be completed by the end of December 2026. This section will likely remain gravel through the winter.