Residents are advised that the Tri County Fire Department will be holding a training exercise at 2771 CTH U in the Town of Pittsfield on Saturday, October 17, starting at 8:00 AM. Expect temporary road closures in the area and plan alternate travel routes if necessary. Please note that this is training only and there is no active incident.
Month: October 2026
School Referendum:
School Referendum: A representative from the Pulaski Community School District will
be present at the October 13th Town Board Meeting to discuss the upcoming
referendum that will appear on the November ballot. The Town Board Meeting will begin
immediately following the adjournment of the Planning Committee Meeting. The
Planning Committee Meeting starts at 6:00 p.m.
Village of Howard Glendale Avenue Sanitary Sewer Construction update.
Because of ongoing issues with the depth of the sewer and dewatering in the past month, Contractor will continue to work on dewatering system early portion of the week. With plans to install sanitary main mid to later part of the week.
Glendale Avenue updated Schedule
- Nature Ridge to Sunny Brook Drive: This segment is anticipated to be completed in November 2026.
- Sunny Brook Drive to Alfred Way: Work on this portion is expected to be completed by the end of December 2026. This section will likely remain gravel through the winter.